Project/company overview
The infrastructure developer is planning to build and operate a deep-water port to provide existing marine traffic with a better place to berth and easier access to a growing region in Australia.
Problem
The organisation has made a concerted effort to reduce the emissions and impact for their proposed development and has a genuine desire to position as Australia’s first ‘green port’, largely powered by renewable energy. As part of the developer’s EPA submission, a GHG emission estimate was required to detail the emissions activities in the construction phase and operation of the port as well as the emissions reduction opportunities.
Approach
Adaptus developed a GHG Management Plan for the development, comprising a Scope 1 GHG emissions baseline. In addition, emissions reducing opportunities were identified through the design, construction, and operations phases in line with the EPA’s GHG Emissions Guidelines. Further, Adaptus developed a Scope 3 emissions estimation framework for the developer to apply as the project matured to evaluate the contribution of customers and suppliers.
Outcome / Value
The GHG management plan was submitted by the developer as part of its Environmental Approvals applications to the EPA and has recently been approved. In parallel, the efforts have been progressed to further investigate the GHG emissions reduction opportunities through the current stage of the development.